Carrier 23XL Dokumentacja Strona 52

  • Pobierz
  • Dodaj do moich podręczników
  • Drukuj
  • Strona
    / 104
  • Spis treści
  • BOOKMARKI
  • Oceniono. / 5. Na podstawie oceny klientów
Przeglądanie stron 51
Table 7 Potentiometer Adjustment
DIAL
ADJUSTMENT RANGE
FUNCTION
FACTORY
SETTING
Minimum
(CCW)
Maximum
(CW)
Starting Current 100% 400% Sets initial starting
current level.
100%
Ramp Time
(Adjustable
Current Ramp)
2
seconds
30
seconds
Sets time during which
current ramps from the
initial starting level to the
maximum possible
current limit setting.
10 seconds
Current Limit 100% 400% Sets maximum
starting current.
250%
Pulse Start 0 (Off) 2 seconds Sets duration of 400%
current pulse. Pulse
is used to break
load free.
OFF
Current Trip 50% 400% Sets running current trip. 175%
Power Saver OFF
CCW Counterclockwise
CW Clockwise
Starting Current The torque required to start a machine
(initial torque) varies from one application to another. Start-
ing current may be adjusted to match the initial motor torque
of the application. The starting current value is adjustable
from 100% to 400% FLA and is factory set at 100%. If quick
acceleration is desired, set the starting current at a higher
level.
Ramp Time (Adjustable Current Ramp) The motor cur-
rent is ramped up from the starting current value over a timed
period set by the ramp time potentiometer (adjustable from
2 to 30 seconds at 400% current limit setting). The 23XL is
factory set at 10 seconds. However, based on jobsite con-
ditions, a range of ±5 seconds is acceptable.
Current Limit This protection limits motor current to a
set value and holds motor torque at a reduced level during
motor start. The current limit is adjustable from 100% to 400%
of the motor full load current value. The current limit is fac-
tory set at 250%.
Pulse Start A pulse start is not used on this machine. It is
set to the OFF position.
Current Trip Acontrol contact closes when the motor reaches
a factory set value of 175% of full load amps. This signal is
used as an interlock to shut down the machine if the motor
stalls (increasing load).
Changing Adjustments The settings are interdependent.
If any setting is changed, the other settings should be checked.
Check the settings in the sequence shown above.
Voltage Measurements Consider the following when check-
ing voltage measurements:
Before energizing the starter, check the incoming lines for
properly balanced voltages.
Close the circuit breaker to apply power to the starter. Verify
the 120 vac control voltage.
Visually check to ensure that all fans are running (if
applicable).
Verify phase sequence at line terminals. Incorrect phase
sequence will result in a shunt trip of the circuit breaker.
Verify that the phase rotation of the lines to the motor is
correct.
If the motor is found to be rotating in the wrong direction,
interchange any two phases to the motor.
Start the unit.
When unit reaches full speed, monitor the running current
to ensure that the motor is not overloaded.
High Altitude Locations Recalibration of the pres-
sure transducers will be necessary since the machine was
initially calibrated at sea level. Please see the calibration pro-
cedure in the Troubleshooting Guide section on page 68.
Input the Design Set Points Access the LID Set
Point menu and view/modify the Base Demand Limit set point
and either the LCW set point, the ECW set point, or Ice Build
set point. The PIC can control a set point to either the leav-
ing or entering chilled water. This control method is set in
the Equipment Configuration menu Config table. See
Fig. 21.
Input the Local Occupied Schedule (OCCPC01S)
Access the schedule OCCPC01S screen on the LID and
set up the occupied time schedule per the customer’s re-
quirements. If no schedule is available, set it for 24 hours
occupied days per week including holidays. This is also the
default setting of the schedule. For this schedule, modify Pe-
riod 1 for ON at 0000 and OFF at 2400 and enable the pe-
riod to be in effect for all days and holidays. For more in-
formation about how to set up a time schedule, read the Controls
section, page 13.
The CCN Occupied Schedule (OCCPC03S) should be con-
figured if a CCN system is being installed or if a secondary
time schedule is required. It normally is input through the
CCN Building Supervisor, but it can also be modified at the
LID.
Fig. 39 Typical Potentiometer Adjustment
52
Przeglądanie stron 51
1 2 ... 47 48 49 50 51 52 53 54 55 56 57 ... 103 104

Komentarze do niniejszej Instrukcji

Brak uwag