39 HQ AiroVisionInstallation, Operation andMaintenance Instructions
10Method 1 Pull the sections against each other, using the pull ropes attached to the lifting bars. Pull evenly on both sides of the AHU. 5.2. Connec
11Figure 17. Fixing the connection stripThis method applies for sections that end with corner posts.Figure 15. Fixing the sealing tape to the joint mu
126. STACKED CASING SECTIONSFor an outdoor installation the plastic roof cover must be finished as described in chapter 8.NOTE: If the AHU needs to co
13Figure 24. Mounting profile, indoor location, unit without intermediate base frameOutdoor Installation• Position the casing sections on top of one a
14Figure 27. roof finish, unit with shorter top section without intermediate base frame • A longer top section needs no further finish at the ends. F
15Figure 30-1. Stacking, indoor location with interme-diate base frameFigure 30-2. Fixing profile, indoor location with inter-mediate base frame There
166.3. Unit with Different WidthsFor units with different widths, there are four different situations. For an indoor installation the method desc-ribe
171234Cross section of width directionFigure 37. - Width direction view, unit of unequal width Figure 38. - Length direction view, unit of unequal wid
18Figure 41. - Unit of unequal width - situation B• Side 1 and 2: Cut the connection profiles to the correct length and mount them on the co
19• Side 1 and 2: Cut the connection profiles to the correct length and mount them on the correct side (see Fig 44).• Side 3: Cut the
Code No: B.8.1.3.i Publication Date: 08082011Revision No: 08082011
20 !CAUTION! Before starting up the AHU ensure that the components have the correct connection voltage and connect them in accordance with the
2210. START-UP INSTRUCTIONS10.1. CasingThe label with the unit data, such as order number, position number etc. is usually located on the acccess cove
2310.7. Dampers10.8. Air Filters10.9.1. General10.9.2. Electric Heaters10.9. Heaters-Check if the actuator motor is installed in accordance with the s
2410.11. Coolers-Check the connections in accordance with the di-mensional drawing.-Control the connections for leaks.-Check drain trap. If Alarko Car
25-Check that the wheel is rotating in the correct direc-tion.This is indicated by an arrow on the casing.-Check if the wheel seals are fitting correc
26!WARNING! Before opening doors, switch off and deenergise the fan, and ensure that it has stopped rotating (minimum of 2 minutes)-Check the splitter
27The checklist contains a general overview of the planning that facilitates the inspections and maintenance of the AHU. On the following pages there
28
29The AHU(s) require little maintenance. The smooth inside and outside finish of the panels makes main-tenance very simple.For dry sections: once a ye
Contents1 - SAFETY CONSIDERATIONS ... 51.1. General ...
30Check once a year for contamination, and if neces-sary clean with compressed air. Check the connec-tions in the control box. Check the operation of
31-First carefully read the instructions from the supplier. The following points require extra attention.-Check the connections of the high-pressure p
32HÜCRE NO: 1 HÜCRE NO: 2 HÜCRE NO: 3 HÜCRE NO: 41 1 2 2 3 31 1 2 2 33Agirlik / Weight (kg):Sip. No / Order No:Hücre No / Cell No:MH...1
33APPENDIX-2 TORBA FILTRE KASET FILTRE B=48mmTORBA+KASET FILTRETORBA+KASET FILTRE(FILTRE BASINÇ FARKI ÖLÇÜMÜ YAPILDIGINDA)KASET FILTRE B=95mmSizdirmaz
34ÖNDEN SÜRMELI TORBA FILTRE MONTAJKAPIPANELÜST GÖRÜNÜSDETAY EDETAY DDETAY CDETAY BDETAY APVC BANT 6x15FILTRE TUTUCU YAYPVC BANT 6x15PVC BANT 6x15 PVC
35COMBINED SIDE WITHDRAWAL FILTER MONTAGE
36F8 – F9 SIDE WITHDRAWAL FILTER MONTAGE
37F7 SIDE WITHDRAWAL FILTER MONTAGE
38W H 287x287 437x287 437x592 592x287 592x592 287x287 287x592 437x287 437x592 592x287 592x592 W H 287x287 437x287 437x592 592x287 592x592 287x287 287x
39APPENDIX-3/2 Front Withdrawal FilterFİLTRE BOYUT ve ADETLERİMODÜL PANEL FİLTRE TORBA FİLTRE MODÜL PANEL FİLTRE TORBA FİLTREW H 292x292 450x300 437x5
10.9.3. Steam Heaters... 2310.10. Siphone
40APPENDIX-4
41: GOSB - Gebze Org. San. Bölgesi, Ş. Bilgisu Cad. 41480 Gebze-KOCAELİ Tel: (0262) 648 60 00 - Fax: (0262) 648 60 08: Sedat Simavi Sok. No: 48, 065
51 - SAFETY CONSIDERATIONS1.1. GeneralThe 39HQ air handling units (AHUs) has been de-signed and manufactured in accordance with the CE machine directi
6Electrical VoltageThis pictogram indicates that there are electrical components behind this access cover, door or panel that may be dangerous for the
72.4. Offloading and HoistingDepending on the dimensions of the AHU and the situation on site, the AHUs are supplied in previously agreed transport se
84. LIFTING INSTRUCTIONS4.1. GeneralThere are transport and lifting instructions attached to the AHU. 4.2. Lifting Bar CertificationThe lifting bars s
9- For hoisting ensure that the weight is evenly dis-tributed and that all previous steps are carried out correctly.If there is not enough space it m
Komentarze do niniejszej Instrukcji