Hook rigging shackles through holes in base rail, as shown in
Detail A. Holes in base rails are centered around the unit
center of gravity. Use wooden top skid, when rigging, to
prevent rigging straps from damaging unit.
UNIT
SIZE
03-07
MAX. WEIGHT
kg
510
SEE
DETAIL A_
PLACE ALL SEAL STRIP
IN PLACE BEFORE PLACING
fUNIT ON ROOF CORg
Fig. 2 -- 50PG Rigging Label
Step 4 -- Field Fabricate Ductwork-- On vertical
units, secure all ducts to roof curb and building structure. Do
not connect ductwork to unit. For horizontal applications, field-
supplied flanges should be attached to horizontal discharge
openings and all ductwork secured to the flanges. Insulate and
weatherproof all external ductwork, joints, and roof openings
with counter flashing fend mastic in accordance with applicable
codes.
Ducts passing through an unconditioned space must be
insulated fend covered with a vapor bmriel:
If a plenum return is used with a vertical unit, the return
should be ducted through the roof deck to comply with applica-
ble fire codes.
A minimum clearance is not requiled around ductwork.
Cabinet return-air static pressure (a negative condition) shall
not exceed 0.35 in. wg with economizer or 0.45 in. wg without
economizer.
Step 5 -- Make Unit Duct Connections
VERTICAL SUPPLY/RETURN CONFIGURATION -- Unit
is shipped in vertical supply/return configuration. Ductwork
openings me shown in Fig. 1 and 3. Attach the ductwork to the
roof curb. Do not attach duct directly to the unit.
For vertical supply and return units, tools or parts could
&op into ductwork and cause fen injury. Install a 90-degree
turn in the leturn ductwork between the unit and the condi-
tioned space. If a 90-degree elbow cannot be installed, then
a grille of sufficient strength and density should be installed
to prevent objects from falling into the conditioned space.
HORIZONTAL SUPPLY/RETURN APPLICATIONS -- Unit
can be field-converted from vertical supply/return to horizontal
supply/return. Remove all screws securing horizontal duct
covers to duct panel. Save panels. Install duct covers in the
vertical duct openings in the basepan with the insulation side
up. Covel.s will drop into openings and can be secured using
field-supplied self-tapping screws. Ductwork can be attached
to duct flanges provided on unit. When securing ductwork to
unit, do not drill in area below bead or above top edge of duct
opening.