e. Open valve 5 fully after the pressure rises above the freeze point of the refrigerant. Open
liquid line valve 7 until refrigerant pressure equalizes.
2. Transfer remaining refrigerant.
a. Close valve 5 and open valve 4.
b. Turn off the water pumps through the LID.
c. Turn off the pumpout condenser water, and turn on the pumpout compressor to push
liquid out of the storage tank.
d. Close liquid line valve 7.
e. Turn off the pumpout compressor.
f. Close valves 3 and 4.
Valve
1a 1b 2 3 4 5 6 7 8 11 12 13 14
Condition
CC C
Valve
1a 1b 2 3 4 5 6 7 8 11 12 13 14
Condition
CCC